Application Filing Timelines (Effective Spring 2007)

Program 1 / Type of Application Application Acceptance Date Application Due Date
 
New Construction
  • Design 2
  • Ongoing Prior to occupancy of any of the classrooms
  • Separate Site 2
  • Ongoing Prior to occupancy of any of the classrooms
  • Construction (Full Adjusted Grant)
  • Ongoing Prior to occupancy of any of the classrooms
     
    Modernization
  • Design 2
  • Ongoing None 3
  • Construction (Full Adjusted Grant)
  • Ongoing None 3
     
    Charter School Facility
  • Notification to District of Intent to File
  • -- At least 30 days prior to submittal of application funding request 4
  • Application Funding Request
  • February 5, 2007 June 5, 2007
     
    Joint Use June 1st of each year May 31st of each year
     
    Small High School After receipt of Academic Reform Strategy score from the CDE September 30, 2007
     
    High Performance Schools Incentive April 2007 5 Until funds have been exhausted
     
    Career Technical Education Facilities
    First Round:
  • CDE Career Technical Education Plan
  • April 2007 5 August 3, 2007
  • OPSC Funding Application Request
  • April 2007 5 October 31, 2007
    Second Round:
  • CDE Career Technical Education Plan
  • August 4, 2007 February 1, 2008
  • OPSC Funding Application Request
  • November 1, 2007 April 30, 2008
    Third Round: 6
  • CDE Career Technical Education Plan
  • February 2, 2008 To be determined
  • OPSC Funding Application Request
  • May 1, 2008 To be determined
     
    Overcrowding Relief
  • First Round
  • May 2007 5 January 31, 2008
  • Second Round
  • February 1, 2008 July 31, 2008
  • Third Round
  • August 1, 2008 January 30, 2009
     
    Seismic Mitigation Fall 2007 5 Until funds have been exhausted

    1 See OPSC Web site and SFP Regulations for application submittal requirements.
    2 Application may only be submitted if the district qualifies for financial hardship assistance.
    3 Applications accepted for reimbursement for any contracts signed after August 27, 1998.
    4 Applies only to charter schools that apply on their own behalf.
    5 Applications may be submitted after approval of the regulations which is anticipated during the timeframe noted. Please check the OPSC Web site for updates.